Sunday, August 19, 2012
Bunker Partial Power Failure
19/8/12 20:20 - We're currently experiencing a partial power failure on the mains at the Bunker datacentre. It appears we have lost one of the phases. Unfortunately under these circumstances the generators did not kick in, a manual override has been applied. Equipment has been running on UPS but some of them have exhausted their battery supplies - as soon as these UPS's have enough charge they will start passing current again and the equipment will power up.
20:40 - SP Confirm single phase failure.
20/8/12 08:30 - All work complete and Bunker verified as back on mains power.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment